As per the allotment order, the scheduled date of commencement of production of coal is 44 months from the date of allotment i.e 29.09.2016. To adhere to the scheduled milestones, WBMDTCL submitted Bank Guarantee of Rs. 42.375 Crore . Till date WBMDTCL is adhering to all the scheduled dates.
Milestone | Date Of Completion | Present Status |
---|---|---|
Mining Lease Application | 28-10-2016 | Mining Lease application submitted to Govt of West Bengal |
Previous Approval | 12-01-2018 | Vide letter No.F.No.13016/01/2017-CBA-llDated 12.01.2018, MoC, Gol has granted Administrative Approval to the GoWB u/s 5(1) of the MM(D&R;) Act,1957 for granting of Mining Lease for Coal. |
Forest Clearance | Not Completed | 1. Proposal No. FP/WB/MIN/26869/2017 for diversion of 109.459 Ha Forest Land has been forwarded by the State Government to H.Q., MoEFCC on 16-01-2019. H.Q, MoEFCC forwarded to Addl. PCCF (Central), Regional Office (EZ), Bhubaneswar for SIR on 21-02-2019. |
Environment Clearance | Not Completed | TOR has been issued by the MoEFCC on 29.09.2017. EIA/EMP reports have been submitted to WBPCB on 16-07-2018. Public Hearing held on 20-09-2018. Minutes of Public Hearing sent by Sr. Environmental Engineer (EIM Cell), WBPCB to the Member Secretary, EAC, MoEFCC, GOI on 04-10-2018. Final EIA/EMP has been submitted to EC Monitoring Cell, MoEFCC, GOI on 25-02-2019. |
Grant of mining lease | 23-02-2018 | Granted by IC&E; Department, GowB vide No. 143- Cl/O/ MIN/GEN-COL/03/2016 dated 23.02.2018. |
Selection Of MDO | Not Completed | Draft RFP along with CMA has been prepared. Govt. Approval is awaited. |